SCHEDULE:
|
Out for Bids |
March 14, 2023 |
|
Mandatory Pre-bid Meeting |
March 29, 2023 at 1:00 pm |
|
Official Bidders List |
March 31, 2023 |
|
Bids Due |
April 12, 2023 at 10:00 am |
|
Post Bid Interviews |
April 12-13, 2023 |
|
Architect Recommendation |
April 14, 2023 |
|
Owner Awards Project |
April 18, 2023 |
|
Notice to Proceed Letters |
April 19, 2023 |
|
Pre-Construction Meeting |
T.B.D. |
|
Physical Construction |
June 19, 2023 – August 18, 2023 |
|
Substantial Completion |
August 18, 2023 |
|
Final Completion |
September 18, 2023 |