Description Date
Out for Bids February 14, 2023
Mandatory Pre-bid Zoom Meeting March 1, 2023 at 3:00 pm
Official Bidders List March 3, 2023
Bids Due March 15, 2023 at 3:00 pm
Post Bid Interviews March 16, 2023
Architect Recommendation March 17, 2023
Owner Awards Project March 21, 2023
Notice to Proceed Letters March 22, 2023
Pre-Construction Meeting T.B.D.
Physical Construction
(School Out of Session) June 19, 2023 – August 20, 2023
Physical Construction
(School In Session) August 21, 2023 – September 22, 2023
Substantial Completion September 22, 2023 or 30 days after substantial completion of each project below (whichever date is greater).
Final Completion October 22, 2023 or 30 days after substantial completion.