Description                                          Date

Out for Bids                                           February 14, 2023

Mandatory Pre-bid Zoom Meeting        March 1, 2023 at 3:00 pm

Official Bidders List                               March 3, 2023

Bids Due                                               March 15, 2023 at 3:00 pm

Post Bid Interviews                               March 16, 2023

Architect Recommendation                   March 17, 2023

Owner Awards Project                           March 21, 2023

Notice to Proceed Letters                      March 22, 2023

Pre-Construction Meeting                      T.B.D.

Physical Construction

(School Out of Session)                        June 19, 2023 – August 20, 2023

Physical Construction

(School In Session)                               August 21, 2023 – September 22, 2023

Substantial Completion                         September 22, 2023 or 30 days after substantial completion of each project below (whichever date is greater).

Final Completion                                   October 22, 2023 or 30 days after substantial completion.