PROJECT TITLE:

Boiler Replacement & Related Work @ Several Locations

 

PROJECT #:

 

26101-26102

 

BRIEF PROJECT DESCRIPTION:

 

Work will include the replacement of the boilers with minor mechanical, electrical, and plumbing modifications to be completed to tie the new boilers into the existing system. In addition there will be minor concrete slab work, wall and floor patching, painting, door and frame replacement, door hardware updates, new lighting, roofing, and other related items will be part of this work.

 

SCHEDULE:

 

Out for Bids

February 9, 2026

Pre-bid Meeting

February 25, 2026

 

     Orchard Center High School at 3:30 pm

 

     Hollywood Elementary School at 4:15 pm

Official Bidders List

February 26, 2026

Bids Due

March 11, 2026 @ 3:00 pm

Post Bid Interviews

March 12-17, 2026

Architect Recommendation

March 18, 2026

Owner Awards Project

March 24, 2026

Notice to Proceed Letters

March25, 2026

All Shop Drawing Reviews Complete

May 22, 2026

Pre-Construction Meeting

May 22, 2026 - Time and Place TBD

Physical Construction

June 15, 2026 – August 14, 2026

Substantial Completion

August 14, 2026

Owner Move-in Date

August 19, 2026

Final Completion

September 14, 2026