SCHEDULE:
Out for Bids |
March 11, 2025 |
|
Pre-bid Meeting |
Raisinville Elementary, March 26, 2025 @ 9:00am Custer II Elementary, March 26, 2025 @ 10:00am Arborwood North Elementary, March 26, 2025 @ 11:00am |
|
Official Bidders List |
March 28, 2025 |
|
Bids Due |
April 8, 2025 @ 3:00pm |
|
Post Bid Interviews |
April 9-15, 2025 |
|
Architect Recommendation |
April 16, 2025 |
|
Owner Awards Project |
April 22, 2025 |
|
Notice to Proceed Letters |
April 23, 2025 |
|
Pre-Construction Meeting |
TBD |
|
Physical Construction |
June 16, 2025 – August 15, 2025 |
|
Substantial Completion |
August 15, 2025 |
|
Final Completion |
|